Page navigation
To access the Demand Planning Accuracy screen, click the Forecast button.
The Forecast button opens the Demand Planning Accuracy screen

The Demand Planning Accuracy page
Data selection
The Historical Data selector gives you access to 2 types of datasets.
The Historical Data selector
- Actual - The historical Sales Out data uploaded into SIMCEL.
- Base Demand - The historical Sales Out data cleaned up of any planned and unplanned demand events.

The Projection Data selector
- Committed Plans - The consolidation of all past plans set as primary (validated for execution), which include the trade and marketing events and their impacts, with an offset of 1 day.

Committed Plans, offset by 1 day
- Committed Plans (90 Days Offset) - The consolidation of all past plans set as primary (validated for execution), which include the trade and marketing events and their impacts, with an offset of 90 days (lag 3).

Committed Plans, offset by 90 days (lag 3)
- Forecast Base - The consolidation of all past forecast baselines, which do not include trade and marketing events, with an offset of 1 day.

Forecast Base, offset by 1 day
- Forecast Base (90 Days Offset) - The consolidation of all past forecast baselines, which do not include trade and marketing events, with an offset of 90 days (lag 3).

Forecast Base, offset by 90 days (lag 3)
- Actual vs Committed Plans (or Committed Plans (90 Days Offset)) - Compare planning accuracy, including any trade and marketing events.
- Base Demand vs Forecast Base (or Forecast Base (90 Days Offset)) - Compare statistical forecast accuracy, excluding any trade and marketing events.
Error metrics
The Error Metrics selector gives access to the accuracy performance metrics.
The Error Metrics selector
- MAE - Mean Absolute Error
- MAPE - Mean Absolute Percentage Error
- MSE - Mean Square Error
- RMSE - Root Mean Square Error
- SMAPE - Symmetric Mean Absolute Percentage Error
- WMAPE - Weighted Mean Absolute Percentage Error
Data granularity
The Product Granularity selector sets the level at which product data is aggregated before the error metrics are computed.
The Product Granularity selector

The Customer Granularity selector

The Time Granularity selector
Analytics
The Error Metrics widget gives a summary of the projection accuracy based on the error metrics you selected. The data is affected by the filters and aggregation levels you chose. As a rule of thumb, the more atomic the data, the less accurate the projection.
The Error Metrics summary widget

The Historical VS Projection Time Series widget

The Historical VS Projection scatter widget

The Volume Vs Error Matrix widget
Metrics computation
If the historical data changes (new data uploaded, base demand adjusted) or the projection data changes (forecast updated, new event allocated to the primary scenario, new primary scenario), click Run Metrics to ensure all the analytics display the latest data.
The Run Metrics button
Export the demand dynamic report
The Demand Dynamic Report, authored by SIMCEL, analyzes product historical sales performance. The report provides insights into overall demand trends, key contributors, and significant outliers. To export the report:Open the report dialog
Configure the report
- Select Analysis Date Range - Choose the period for the report analysis.
- Select Time aggregation level - Select how you want to aggregate time data (monthly, quarterly).
- Channels (optional) - Define a subset of customer segments.
- Select Segment Group - Choose the aggregation level for historical demand and forecast data, such as brand, category, or channel.
- Select UoM - Specify the unit of measurement for analyzing historical demand and forecast data.
- Set outlier coefficient (# stddev multipliers) - Set the number of standard deviation multipliers for outlier detection and analysis. This helps identify significantly high or low sales volumes during the selected period (see the 68-95-99.7 rule).
- Set threshold for # Top Contributors - Establish the number of top contributing segments (for example, brands or product IDs) to highlight in the report. This is the absolute threshold.
- Set threshold for % contribution of Top Contributors - Define the percentage threshold that identifies top contributors by their share of total demand, sales volume, and so on. If the number of contributors exceeding this percentage surpasses the absolute threshold, it is adjusted to match the absolute threshold limit.
- Select Date Range to evaluate Top Contributors - Select the time frame for identifying top contributors, based on their contribution to sales or demand within the last year or another defined period. For example, you may only care about brands that make up 80% of sales in the last 12 months.
Generate the report

The Pre-Forecast Report configuration dialog